The contractor of this fit out project engaged Hera Engineering for mid-way through the job after encountering several structural-related setbacks. An important issue was the installation of numerous new roller doors and mechanical services, which were obstructed by the existing timber roof structure. The contractor required a solution with minimal modifications to the existing structure whilst still allowing the fit out to continue unimpeded by temporary propping.
This practical site project is another example of our willingness to think ‘outside-the-box’ and ability to solve complex problems with a practical solution. We are equally committed to find the best solution for the client, regardless of the project size or budget. This positive and creative approach has seen Hera Engineering quickly develop a reputation for delivering innovative and practical engineering solutions.
We were also appointed to undertake full glazing facade design.